A downtown tower or mixed-use building does not close because one floor is wet. Tenants on other floors expect normal access, quiet, clean air and working elevators. That means restoration work is planned in phases, with some tasks done during business hours and others moved to evenings or weekends where the building allows it.

Most commercial buildings have contractor rules covering insurance requirements, working hours, freight elevator reservations, dock time, hot work permits and how materials leave the building. A restoration contractor should ask for these on the first day. If the rules are not written down, now is a good time to write them.

Which work goes where in the schedule

  • IfThe task is emergency extraction or stopping active waterThenIt happens immediately, regardless of time, with security informed.
  • IfThe task is loud: demolition, core drilling, heavy debris removalThenUsually scheduled outside business hours or in agreed quiet windows.
  • IfThe task makes dust, such as cutting drywall or sandingThenDone inside containment with negative air, and timed to avoid peak elevator traffic.
  • IfThe task is monitoring and moisture readingsThenOften fine during the day, with a short check-in at the management office.
  • IfThe task requires shutting a shared system, such as water to a riser or an air handlerThenScheduled with advance notice to affected tenants, typically after hours.

Building resources to reserve

Resource
Freight elevator
Why it matters
Equipment in, debris out, without using passenger cars
Who usually controls it
Property management or the security desk
Resource
Loading dock
Why it matters
Dumpsters, box trucks and equipment deliveries
Who usually controls it
Property management; shared with tenant deliveries
Resource
Street or alley space
Why it matters
Containers or lifts outside the building
Who usually controls it
City right-of-way permits may be required; check with Denver's transportation department
Resource
After-hours access cards
Why it matters
Crews working evenings and weekends
Who usually controls it
Security
Resource
Electrical capacity
Why it matters
Dehumidifiers and air movers draw heavy loads
Who usually controls it
Building engineering
Resource
HVAC schedule
Why it matters
After-hours air helps drying and controls odor
Who usually controls it
Building engineering

Keeping other tenants on side

Unaffected tenants mostly want to know three things: how long the work will last, when it will be noisy, and whether the air is safe. A brief notice at the start, plus updates when the schedule changes, prevents most complaints. Post signs at elevator lobbies on affected floors and keep containment tidy and clearly marked.

If tenants raise concerns about dust or odor, take them seriously. Ask the contractor to show how containment and air filtration are set up, and consider independent air testing where materials such as mold or older building components are involved.

General information for Downtown Denver, not a quote or professional advice. In an emergency, call 911.